2020 Road Improvements Program

Project:

2020 Road Improvements Program (Contract #2193)

Town Contact:

Stephane Cherduville, Public Works Engineer, Concord Public Works – Engineering Division, 978-318-3210, scherduville@concordma.gov

General Contractor:

Newport Construction Corporation

Project Overview:

The 2020 Roads Program has been contracted to Newport Construction Corporation of Nashua, NH for $455,625.51. The scope of work includes the reclamation and repaving of Park Lane, Lewis Road, Warner Street, and Bedford Court. Additionally, Partridge Lane has been identified to receive a mill and overlay treatment. 

Construction Update:

Construction was originally slated to begin in the fall of 2020, but the Engineering Division postponed the start of construction until the spring of 2021 due to numerous inquiries and requests from residents to extend or update their utilities in the Right of Way. Newport Construction is scheduled to begin the work in early May 2021, impacted residents will be contacted with most recent schedule once it becomes available.


Updated 4/6/21