2021 Road Improvement Program Bid

           Project:

2021 Road Improvements Program (Contract #2023) 

General Contractor:
Newport Construction

Town Contact:
Stephane Cherduville, Public Works Engineer, Concord Public Works – Engineering Division, 978-318-3210, scherduville@concordma.gov

Bids for this project were open on April 15, 2021 - the Engineering staff with Hayner Swanson, Inc. (HSI) assistance analyzed the bid tenders and recommended the contract be awarded to Newport Construction which was the lowest responsible bidder.

The 2021 Roads Program contract with Newport Construction Corporation includes the reclamation and repaving of Peter Spring Road, Prescott Road, Arrowhead Road, Cranefield Road and Minuteman Drive. 
Newport Construction started the catch basin cleaning work on May 27, 2021



Construction Update April 2022:

Construction of the 2021 Roads Program that includes Arrowhead Road, Cranefield Road, Minuteman Drive, Peter Spring Road, and Prescott Road is completed and is now under warranty. The contractor will be addressing some punch list items in the spring of 2022.

2021 Mill and Fill Paving Program:

Concord Public Works has also identified areas in town which requires more in-depth, localized treatment of the road surface to extend its serviceable life.  As such, the following locations have been identified to receive “mill & fill” treatments, and are included as part of the 2021 Road Improvement Project tender package:

LOCATION

LENGTH

WIDTH

SQ. YDS

SCHEDULED

Lang @ Monument St.

16

25

44

Spring 2022

1597 Monument St.

12

13

17

Spring 2022

Sudbury St. at Grant St.

45

14

70

Spring 2022

Laws Brook Rd @ Warner St.

33

10

37

Spring 2022

845 Barret Mills Rd.

26

21

61

Spring 2022

560 Old Bedford Rd

20

12

27

Spring 2022


LOCATION

LENGTH

WIDTH

SQ. YDS

 Completed

Old Pickard Rd (Various locations)

1271

Yes

Sorrell Rd. $ Shagbark Rd.

75

26

217

Canceled

Elm St, (Various locations)

643

Yes


Based on the availability of funding sources additional roads are to be selected by Engineering Staff, to also be reconstructed or to receive a mill & fill treatment  during the 2021 construction season.

Construction Update October 2021:

Newport Construction completed the mill and fill areas on Old Pickard Rd and Elm Street. The remaining areas will be completed in the spring of 2022