2022 Roadway Improvements Project

As part of the 2022 Road Improvement Project, Engineering staff advertised three (3) separate contracts listed below:

  • Phase I - pavement preservation with asphalt rubber 
  • Phase II - pavement preservation and rehabilitation that includes fog sealing, microsurfacing, and cold in-place recycling 
  • Phase III - pavement reconstruction that includes full depth reconstruction and milling and overlay

Bids for Phase I opened on March 2, 2022.   Engineering staff analyzed the bid tenders and recommended the contract be awarded to All States Construction Inc. The Engineering staff is currently working with the Town House and the Contractor to get the Phase I contract executed. Construction is anticipated to begin at the end of the month of April 2022.

Bids for Phase II opened on March 31, 2022.   Engineering staff is currently analyzing the bid tenders. A decision of award on this bid package will be made within the next two weeks.

Engineering staff has requested bids for Phase III on March 25, 2022, and the bid opening is scheduled for April 22, 2022. If the bid process is successful, construction is anticipated to begin in May 2022.

The three phase of the 2022 Roads Improvement Program will include the following streets and treatments. 

Roads chosen for Rehabilitation

Street Name

From Street Name

To Street Name

Planned Repair Method

Alford Ci

Mattison Dr.

Cul-De-Sac Loop

RECONSTRUCTION

Autumn Ln

Lincoln Town line

Cul-De-Sac Loop

RECONSTRUCTION

Ayrshire Ln

Mattison Dr.

Cul-De-Sac Loop

RECONSTRUCTION

Mattison Dr.

Williams Rd

Mattison Dr.

RECONSTRUCTION

Old Mill Rd

Harrington Av

Range Rd

RECONSTRUCTION

Stacey Cir

Old Mill Rd

Cul-De-Sac Loop

RECONSTRUCTION

Alden Rd

Plainfield Rd

Cul-De-Sac Loop

RECONSTRUCTION

Anson Rd

Alden Rd

Plainfield Rd

RECONSTRUCTION

Raymond Rd

Plainfield Rd

Cul-De-Sac Loop

RECONSTRUCTION

Pheasant Ln

Lincoln Town Line

Cul-De-Sac Loop

RECONSTRUCTION

Commonwealth Av

Church St

Laws Brook Rd

RECONSTRUCTION

*Bradford St

Commonwealth Av

Dead End

MILL AND OVERLAY

*Coolidge Rd

Main St

Oak Rd

MILL AND OVERLAY

*Davis Ct

Bedford St

Dead End

MILL AND OVERLAY

+Florio Dr.

Main St

Cul-De-Sac Loop

MILL AND OVERLAY

Macmillan Dr.

Mattison Dr.

Cul-De-Sac Loop

MILL AND OVERLAY

Monument

Sawmill Brook

150' North

MILL AND OVERLAY

+Pine St

Main St

Cold Seam

MILL AND OVERLAY

*ORNAC

Sudbury Rd

Williams Rd

MILL AND OVERLAY

*Winthrop St

Commonwealth Av

End

MILL AND OVERLAY

*Locations postponed to next year due to National Grid main replacement not yet completed

+Locations also postponed to next year due to their completed proximity to the above locations

Roads chosen for Preservation Techniques:

Street Name

From Street Name

To Street Name

Planned Repair Method

Annursnac Hill Rd

College Rd

Annursnac Hill 

ASPHALT RUBBER

Annursnac Hill Rd

Strawberry Hill Rd

College Rd

ASPHALT RUBBER

Farmer's Cliff

Lowell Rd

Cul-De-Sac

ASPHALT RUBBER

Barretts Mill Rd

Rt 2

College Road

ASPHALT RUBBER

College Rd

Annursac Hill

Barretts Mill Rd

ASPHALT RUBBER

Hildreth Ln

Lowell Rd

Cul-De-Sac

Cape Seal (Asphalt Rubber + Microsurfacing)

Prairie St

Dead End

Chase Rd

 MICROSURFACING

Prairie St

Main St

Brown St

 MICROSURFACING

Wright Rd

Laws Brook Rd

Cul-De-Sac Loop

 MICROSURFACING

 

2022 Roads Program