AMS Project Status
January 2025 - June 2025
Meter technicians continue to install the last remaining residential and commercial AMI meters. The "last mile" of meters to be installed will be at a slower pace due to appointments needing to be coordinated with commercial property managers and residents. CMLP's electrician completed installations of the new load control switches, and our previous load control system will be decommissioned in the upcoming months.
January 2025 - March 2025
Meter technicians continue to install the last remaining residential and commercial AMI meters. The "last mile" of meters to be installed will be at a slower pace due to appointments needing to be coordinated with commercial property managers and residents. CMLP's electrician completed installations of the new load control switches, and our previous load control system will be decommissioned in the upcoming months.
September 2024 - December 2024
Meter technicians are wrapping up the installation of new residential electric meters and load control switches in Concord and have begun to install new meters at Concord businesses. We are also completing the installations of new load control switches.
May 2024 - September 2024
Meter technicians continue to install new residential electric meters and load control switches throughout the rest of Concord. Once the residential meters meter installations are complete, we will begin working with Concord businesses to install their new meters.
December 2023 - May 2024
Meter technicians are installing new electric meters and load control switches in the West Concord area.
November 2023
Meter technicians installed 10 residential electric meters, reviewed lessons learned in late November, then began installing new meters and load control switches.
October 2023
Testing of residential meters, meter data files, bill print programming, and load management devices underway with a target completion of late October.
September 2023
Thorough testing of residential meters and load management devices underway with a target completion of mid-October.
August 2023
Load management devices arrived. Test set of residential meters installed.
July 2023
Additional residential meters arrive. Integration testing delayed due to availability/change of vendor resources. The first residential meters tentatively planned to be installed in July are now pushed to late August or early September.
May 2023
First set of residential meters arrive. Integration testing to begin.
March 2023
Communication equipment and software arrive.
November 2022
Eaton was onsite with CMLP and CPW for the project kickoff and requirements gathering during the week of November 7th.
September 2022
CMLP executed the Advanced Metering System contract and Purchase Order with Eaton in September of 2022. Following the contract execution, Eaton and CMLP have begun the procurement process for electric meters, equipment, and water nodes. Due to ongoing supply chain delays, the approximate delivery times for the various meters and water nodes range from 26 weeks to 61 weeks.
November 2021
CMLP issued a Request for Proposal for an Advanced Metering System. CMLP received nine proposals in response to the Request for Proposal. After a very thorough evaluation process, CMLP selected the Eaton Corporation AMS solution. The AMS Vendor Recommendation with details about the evaluation and selection process can be found here.
November 2020
CMLP issued the Consulting Services for a Metering and Communications System(s) Specification and Selection Request for Proposal (RFP) to identify and hire an expert to help us select a new system. Go to pages 14-19 for a description of the Scope of Work and Deliverables. CMLP hired Lemmerhirt Consulting as the technical lead on the AMS vendor selection project.